浅谈高压开关柜的停电、送电和接地线操作规范

发布日期:2018-01-19 作者:贵阳开关柜 点击:

浅谈高压开关柜的停电、送电和接地线操作规范

Discussion on the operation specification of power stop, power supply and grounding wire for high voltage switchgear

贵阳开关柜

贵阳开关柜提醒关于高压开关柜的操作已经形成了标准化的规范,比如说它的停电的操作应按照开关、负荷侧刀闸、电源侧刀闸顺序依次进行,而送电的倒闸操作则正好与上述顺序相反,同时还要注意严防带负荷拉合刀闸。

Guiyang switchgear remind has formed a standard specification of high voltage switchgear operation, such as its power operation should be carried out in turn according to the switch, load side switches, power supply side switches sequentially, and switching power supply is just the opposite order, but also should pay attention to prevent pulling with load knife gate.


在对高压开关柜进行操作之后,必须还要进行效果检查,若某一个操作任务中有一回路转热备用的话,则拉开开关后的效果检查必须单独经性;其他情况应由拉开、合上刀闸前检查开关的实际位置来代替。

After the operation of the high voltage switch cabinet, must check the effects, if there is a loop to standby if a task is started, check the effect after the switch must be separately by sex; other circumstances should open and close the switch check before switch to replace the actual position.


当高压开关柜需要重合闸装置投入的话,停用操作程序应随开关拉开、合上而停用、投入;送电时重合闸装置应在开关合上后投入,停电时重合闸装置应在开关拉开前停用。在对高压开关柜装设接地线时,应先装设调度管理的接地线,再装设变电所自管的接地线;拆除接地线时顺序与此相反。

When the high voltage switchgear needs reclosing device input, the shutdown operation procedure should be switched off and input with the switch open and close. When the power supply is reused, the reclosing device should be put on the switch after being switched on. When the power fails, the reclosing device should be switched off before the switch is pulled apart. When installing the grounding wire for the high voltage switchgear, the grounding wire for dispatching management should be installed first, then the grounding line of the substation will be set up, and the grounding line will be removed in opposite order.


高压开关柜装设接地线时,执行验电后应立即装设接地线的规定;若是还需要在开关柜内开关两侧装设接地线时,应在开关两侧分别验电后再分别装设接地线,要分步进行。贵阳开关柜小编今天就分享到这里了。

When installing the grounding wire in the high voltage switchgear, the grounding wire shall be installed immediately after the inspection is carried out. If the grounding wire is installed on both sides of the switch cabinet, it is necessary to check the electricity on both sides of the switch and install the grounding wire separately. The small Guiyang switch cabinet is here today.